Installation of Alfa Laval PureSox Scrubber System
Project Name | Installation of Alfa Laval PureSox Scrubber System |
---|---|
Vessel Name | VLCC FRONT LINE DISCOVERY |
Yard | MMHE, Pasir Gudang |
Year | 2019 |
Achievement | 5,760 man-hour without LTI |
Project Scope | To install the major components of Alfa Laval PureSox Exhaust gas scrubbing system in MMHE shipyard in Pasir Gudang. Pre-fabricated column, pipes and new valves were delivered by Client to yard. Our team assist to open up the packing, transported and lifted each and every components and fitted into their positions. The smaller being DN100 pipe and valve, and the largest was as large as 1900mm diameter exhaust pipe and main stop valve. |
Other Album
Busbar Modification
2 photos
Cable Pulling & Cable Laying
7 photos
Cable Termination & Cable Dressing
9 photos
Cable Tray Installation
4 photos
Delivery
8 photos
ELECTRICAL WORKS
6 photos
Flow Meter Installation
2 photos
IGG Modification on LNG Tanker
9 photos
Large Flowmeter Replacement
5 photos
Lifting Methanol Column
3 photos
Orbital Welding
3 photos
Roof & Cladding Installation
4 photos
Site Installation
1 photos
Stainless Steel Pipe Installation
7 photos
Steam Tracing
3 photos