Project Reference
1
“LeesGreen” IMO Approved Ballast Water Management system
16
Headway BWTS Installation
25
Sunrui BWTS installation
10
Alfa Laval Pureballast BWTS installation
41
Blue Ocean Shield BWTS
7
Stainless Steel Pipe Installation
3
Electrical Hydraulic Valve Control Panel Installation
3
Steam Tracing
2
Flow Meter Installation
4
Roof & Cladding Installation
9
Cable Termination & Cable Dressing
7
Cable Pulling & Cable Laying
4
Cable Tray Installation
2
Busbar Modification
3
On-Site Main Switchboard (MSB) Modification
4
Heat Exchanger Cleaning & Maintenance
3
Lifting Methanol Column
7
UV Sterilizer Installation & Commissioning
4
10" Cooling Tower Water Supply & Return Pipeline
5
Large Flowmeter Replacement
6
ELECTRICAL WORKS
6
Insulation Work ( Vessel , Tank , Piping )
9
IGG Modification on LNG Tanker
6
500TPD CPO Washing & Pretreatment Plant
2
Others